All Simple - Notice history

All systems operational

Notice history

Apr 2026

Telephone Support Unavailable
  • Completed
    April 24, 2026 at 5:00 PM
    Completed
    April 24, 2026 at 5:00 PM
    Maintenance has completed successfully
  • In progress
    April 24, 2026 at 8:00 AM
    In progress
    April 24, 2026 at 8:00 AM
    Maintenance is now in progress
  • Planned
    April 24, 2026 at 8:00 AM
    Planned
    April 24, 2026 at 8:00 AM

    Telephone support will be temporarily unavailable during the period.

    All other support channels remain fully operational and are being monitored as normal.

    How to reach us during this time:

    Tickets and emails will be responded to as normal. Hosting, VPS, and all other services are unaffected by this notice.

    Thank you for your understanding.

Telephone Support Unavailable
  • Completed
    April 23, 2026 at 5:00 PM
    Completed
    April 23, 2026 at 5:00 PM
    Maintenance has completed successfully
  • In progress
    April 23, 2026 at 8:00 AM
    In progress
    April 23, 2026 at 8:00 AM
    Maintenance is now in progress
  • Planned
    April 23, 2026 at 8:00 AM
    Planned
    April 23, 2026 at 8:00 AM

    Telephone support will be temporarily unavailable during the period.

    All other support channels remain fully operational and are being monitored as normal.

    How to reach us during this time:

    Tickets and emails will be responded to as normal. Hosting, VPS, and all other services are unaffected by this notice.

    Thank you for your understanding.

[LON1] Data Centre Scheduled Maintenance 23/04/2026 08:00 to 16:00
  • Completed
    April 23, 2026 at 12:52 PM
    Completed
    April 23, 2026 at 12:52 PM
    Maintenance has completed successfully.
  • Update
    April 23, 2026 at 9:55 AM
    Update
    April 23, 2026 at 9:55 AM

    Here is an update with further timings from the data centre team:

    We'll be beginning the manual load shifting process imminently at ~10.20am, after which point the upgrade works on the substation will begin, which are expected to take until ~12.20pm. Once this work is complete and tested, we'll manually move the load back across and return to normal operation - we'll update you again once this is complete.

  • In progress
    April 23, 2026 at 7:00 AM
    In progress
    April 23, 2026 at 7:00 AM
    Maintenance is now in progress
  • Planned
    April 23, 2026 at 7:00 AM
    Planned
    April 23, 2026 at 7:00 AM

    We have been advised by our data centre partner, that they will be running maintenance next Thursday during the day, please see further information below:

    The works to be carried out in this window will include:

    - Upgrade to substation supply

    This work is being undertaken to ensure ongoing high-quality service delivery to all customers. Please see below for a basic summary of impact per action:

    Upgrade to substation supply
    We are upgrading the substation supply at our Netwise London East facility to enable additional power capacity for the active footprint of the data centre. During this window, the substation metering will be upgraded, during which time we will failover to our backup generator system to enable this work to go ahead safely. The window given here is the full extent of the time estimate for works to begin, however the actual work itself is expected to take less than two hours within this given time window. The move across to generator supply will be seamless and actioned manually ahead of the active portion of the works beginning, with no impact to client deployments.

    Please treat this window as 'at risk'. While overall power redundancy will be reduced during the active works portion of this window, there is no expected impact to client systems during this time.